Auburn fire panel approves $264,946 change order for site work

Other Committee · Meeting of September 15, 2026

Auburn fire station panel approves $264,946 in change orders, weighs $450,000 fix for a bay too narrow for truck jacks. The Fire Station Building Committee unanimously approved a $230,430.92 payment for final underground ledge removal and a $34,515 site-work package linking the station's parking lot to an adjacent park and the neighboring Dunkin' Donuts lot, for a combined $264,945.92. Members also approved Pay Requisition No. 4 for $1,041,954.71, with the project reported at 15.57 percent complete.

The Fire Chief and a presenter identified as Glenn told the committee that earlier value-engineering cuts, which trimmed 950 square feet and saved more than $700,000, narrowed the mechanic's bay to about 18 feet, leaving no room for the originally planned truck jacks and no way to lift the department's ladder truck. A proposed in-ground lift system, priced at roughly $270,000 for the units alone, carries a working estimate "not to exceed $450,000." One member invoked the project's $4.2 million in bid savings, warning against "the $3,000 decision in 1964 not to upgrade the steel." No vote was taken because the item was not on the agenda.

In the full story:

  • Who Was There
  • Organizations And Documents Referenced
  • The complete report — 2,622 words

Source: the Other Committee meeting of September 15, 2026, reported from the official video recording and transcript.

Keep reading with a 30-day free trial

Subscribe to Auburn News to keep reading this post and get 30 days of free access to the full post archives.

Already have an account? Sign in. Ask about this instead

Starting a trial requires a payment method. After 30 free days your subscription begins at the price shown at checkout and renews automatically until you cancel. You can cancel anytime from your account. Subscription terms

A subscription gets you:

  • Subscriber-only posts and full archive
  • Post comments and join the community
  • 24x7 access to local news

Subscribe to Auburn News

Don’t miss out on the latest issues. Sign up now to get access to the library of members-only issues.
jamie@example.com
Subscribe